Project tracker + reported explainer

India semiconductor projects, factory status and capacity

Track India’s 12 approved semiconductor projects, see which five entered commercial production, and compare capacity claims by manufacturing stage.

Read MeitY’s latest production and project approval summary
Rainbow-reflecting circular 300 mm silicon photonics wafer
A 300 mm silicon photonics wafer photographed in March 2015. Photograph resized and converted to WebP. · Ehsanshahoseini · CC BY-SA 4.0

Which semiconductor projects were producing commercially?

India had approved 12 semiconductor projects under Semicon 1.0, and five had commenced commercial production as of October 2026, according to the Ministry of Electronics and Information Technology’s November 6 update. The five were Micron, Kaynes and CG Semi in Sanand, CDIL’s discrete devices line in Mohali, and Suchi Semicon’s packaging line in Surat.

The September 17 ministry record supplies the names and milestone dates behind that October count. Four entries are in Gujarat, including three distinct facilities in Sanand and one line in Surat. The fifth is in Punjab. The project or line is the useful unit to track because a single industrial location can have several operators, each with its own start date and manufacturing scope.

Download this table (.csv)

Commercial production milestones recorded in 2026
Project or lineLocationCommercial milestoneActivity
MicronSanand, GujaratFebruary 28Assembly and test
KaynesSanand, GujaratMarch 31Outsourced assembly and test
CG SemiSanand, GujaratJuly 4Commercial chip packaging
CDIL discrete devices expansionMohali, PunjabSeptember 17Discrete devices
Suchi SemiconSurat, GujaratSeptember 17Chip packaging

The September record described Tata Electronics’ Dholera silicon fab and its Jagiroad assembly and test project as under construction. For the other projects without a named commercial milestone, the approval records establish their inclusion in the portfolio. Construction progress, equipment installation and trial activity require separate evidence for each site. The portfolio count alone gives no basis for assigning those stages.

Read the date column as a record of when commercial activity began at the named facility or line. Suchi’s May approval and September line launch, for instance, answer two separate questions about the same Surat project. A further question, how much the company actually produced in the months after launch, calls for production figures covering that period.

How three Sanand projects reached production

Micron’s timeline shows how several valid dates can circulate for the same facility. A memorandum of understanding was signed in June 2023, the groundbreaking followed in September 2023, and pilot machinery installation began in February 2024. Micron dates commercial assembly and testing to February 28, 2026. Each date describes a specific event, so the answer to when the project started depends on which event the reader needs.

At the opening, Micron presented its first shipment of India-made memory modules to Dell Technologies. That identifies a product and customer associated with the commercial milestone. The activity Micron documented at Sanand was assembly and testing. Establishing where the wafers were fabricated would require evidence that identifies the wafer fabrication site.

Kaynes’ March 31 inauguration came with an official production start for its Sanand operations. CG Semi has a different sequence. Its foundation stone was laid in 2024, semiconductor testing was underway by August 2025, and its commercial chip packaging inauguration took place on July 4, 2026. Use July 4 to compare CG Semi with Kaynes and Micron on commercial starts, and keep August 2025 if the question concerns when CG Semi had reached testing.

Micron also forecast that it would assemble and test tens of millions of chips in 2026 and hundreds of millions in 2027. Those figures describe expected activity over calendar years. To assess the ramp, look for a later disclosure covering the same activity and period. A shipment announcement establishes that a shipment occurred, while a forecast gives the company’s expectation for volume.

What the capacity figures measure

Front-end fabrication forms devices on wafers. Assembly, testing, marking and packaging, abbreviated ATMP, prepares components and verifies their performance. OSAT refers to outsourced semiconductor assembly and test. These distinctions matter when a government table puts wafer starts and packages side by side. A wafer start counts a wafer entering fabrication. The number of usable chips produced from it depends on factors including the die size and the yield.

The April 1 Lok Sabha written answer records capacity and announced investment for the first ten approved projects. The May 5 Cabinet release adds capacity claims for Crystal Matrix and Suchi Semicon. The figures describe the scope of each approved project. They retain the time periods and units used in the official statements, including weekly assembly and test units, monthly wafer starts and annual discrete device units.

Download this table (.csv)

Approved projects and the capacity figures published for them
ProjectStateAnnounced investmentPublished capacityVerified stage
Micron ATMPGujarat₹22,516 croreAround 14 million units/weekCommercial start documented in 2026
Tata–PSMC Dholera silicon fabGujarat₹91,526 crore50,000 wafer starts/monthUnder construction at 17 September update
Tata Jagiroad OSATAssam₹27,120 crore48 million units/dayUnder construction at 17 September update
CG Semi OSATGujarat₹7,584 crore15.07 million units/dayCommercial start documented in 2026
Kaynes OSATGujarat₹3,307 croreOver 6.33 million chips/dayCommercial start documented in 2026
Vama Sundari InvestmentsUttar Pradesh₹3,706 croreAround 20,000 wafers/month and 36 million chips/month, reported as separate metricsApproval and capacity published
3D Glass SolutionsOdisha₹1,943 crore5,800 glass substrate panels/month, 4.20 million assembly units/month and 1,100 heterogeneous integration units/monthApproval and capacity published
SiCSemOdisha₹2,066 crore5,000 silicon carbide wafers/month and 8 million packaging units/monthApproval and capacity published
CDIL discrete devices expansionPunjab₹117 crore158.38 million units/yearCommercial start documented in 2026
ASIP packagingAndhra Pradesh₹480 crore96 million units/yearApproval and capacity published
Crystal MatrixGujaratAbout ₹3,936 crore jointly with Suchi72,000 m² of display panels/year and 24,000 sets of RGB epitaxy wafers/yearApproval and capacity published
Suchi Semicon OSATGujaratIncluded in the joint figure above1,033.20 million chips/yearCommercial start documented in 2026

SiCSem’s two figures are useful for a reader asking whether its Odisha project includes fabrication and packaging. The silicon carbide fab has a published capacity of 5,000 wafers per month, and the packaging stage has a published capacity of eight million units per month. To relate the two figures, the reader would need details on the devices made from those wafers and how the fab’s output would feed the packaging operation.

The three figures for 3D Glass Solutions describe three stages in Odisha. Substrate panels, assembly units and heterogeneous integration units have different definitions, even though all three figures are monthly. For Vama Sundari Investments, the record gives wafer and chip figures separately. Keep both with their original labels so a reader can see exactly which quantity each figure describes.

Suchi’s approved 1,033.20 million chips per year describes its design capacity. The September 17 announcement establishes that a commercial line launched. A claim about annual output needs a defined production period and actual counts. A claim about utilization also needs the available capacity for that same period, which can change as lines come into service.

Read the unit and the date before comparing two plants. The approved stand-alone Tata Dholera figure is 50,000 wafer starts per month. The Jagiroad packaging capacity is given as 48 million units a day. A wafer start and a packaged unit describe different stages and have different denominators. The commercial-launch dates show that specific named lines began producing commercially. That milestone and the design figures leave actual October throughput and utilisation unreported in the cross-project release.

Where the Tata projects and the two Dholera facilities stand

Tata Electronics’ two projects occupy different parts of the supply chain. The Tata–PSMC project at Dholera in Gujarat is a 300 mm silicon fab with an announced capacity of 50,000 wafer starts per month. The Jagiroad project in Assam is an outsourced assembly and test facility with announced capacity of 48 million units per day. Tata described both as under construction at the September 17 event.

The Dholera fab also appears in an official table dated April 9, 2026, which records its special economic zone approval. That administrative milestone establishes SEZ status. Evidence of commercial fabrication would come from a later announcement or disclosure explicitly identifying the Dholera site and the start of commercial wafer production. The September construction update is the latest dated site status in the reviewed ministry material.

The official records attach two investment estimates to the Dholera fab. The Lok Sabha project statement gives ₹91,526 crore, and the SEZ record gives an estimate of ₹91,000 crore. Each belongs with the scope and date of its publication. Those two records alone give no basis for calculating a change in project spending.

Crystal Matrix Limited also has an approved project in Dholera. The May 5 Cabinet release describes a compound semiconductor fab with assembly, test, marking and packaging for mini and micro LEDs. It lists proposed display panel area and sets of RGB epitaxy wafers per year. A headline about a Dholera fab therefore needs an operator and a product description before it can update either project’s timeline.

How approvals and mission budgets fit together

The portfolio grew from ten projects in the April 1 parliamentary answer to twelve after the Cabinet approved Crystal Matrix and Suchi Semicon on May 5. Those two approvals carried a joint announced investment of about ₹3,936 crore. In July, the ministry classified the portfolio as one silicon fab, one compound fab with packaging, one gallium nitride display fab with packaging, and nine assembly and test projects.

The twelve approved projects span Gujarat, Assam, Uttar Pradesh, Punjab, Odisha and Andhra Pradesh. The November update puts cumulative announced investment above ₹1.64 lakh crore. That figure describes commitments across the approved projects. A reader seeking spending already incurred would need company disclosures or government records that report actual expenditure and identify which costs and projects are included.

The mission’s fiscal outlays describe government programme funding. Semicon 1.0 was approved in December 2021 with ₹76,000 crore. The Cabinet approved a ₹127,500 crore fiscal outlay for Semicon 2.0 on July 15, 2026. Use those amounts to compare the two programme approvals. Use announced investment to describe the amount attached to the portfolio of individual projects.

On November 6 a portal opened for Pillars 2 through 4 of Semicon 2.0. The portal marks the opening of an application route. The same release also mentions twelve applicants under the separate Electronics Components Manufacturing Scheme. To decide whether to change the semiconductor project count, check the name of the scheme and look for an approval naming the project, its operator and its location.

How to verify a new production or capacity claim

Start with a dated ministry, Cabinet or company record and match the operator, site and activity to the project entry. Read past the headline to find the event date and the verb the issuer uses. A release can publish a retrospective account of a groundbreaking, describe equipment installation already underway and give a future production target in the same document. Each statement belongs at its own date and stage.

If a company announces a new line at an existing site, check whether the release describes trial runs, a commercial start or an expansion of available capacity. For an expansion, look for the particular line and any figure that says whether the increase is incremental or the new site total. The distinction decides whether to add a dated event, revise the capacity field, or update both.

The reviewed cross-project record gives no measured site-level throughput, utilization or yield for October or November. For a later claim about throughput, look for a reported count tied to a facility, product and period. Check whether the count refers to wafers started, chips assembled and tested, or units shipped. If a release gives only a group-wide figure, the individual site’s contribution remains undisclosed unless the company provides a breakdown.

For yield, look for a definition of what passed and at which stage it was measured. A packaging test result and a wafer fabrication yield answer different manufacturing questions. Public project records are usually enough to date an approval or commercial launch. Assessing whether a plant is producing consistently at its stated scale requires operating disclosures with comparable units and periods.